About Trailblazer Village
Campbell, California is recognized for its numerous parks, natural surroundings, and energetic neighborhood. The southwest Campbell neighborhood of Trailblazer Village is only five miles from Campbell’s downtown and popular shopping areas, and it is nine miles from downtown San Jose. The San Jose International Airport is about 10 miles away, making this community a convenient location for those who are traveling for business or pleasure.
Trailblazer Village Homes
Single-family homes with modern American craftsman accents are common in this neighborhood. No matter what phase of your life you’re in, these floor designs, which have square footage ranging from 2,447 SF to 3,994 SF, are excellent. These houses are versatile and appealing thanks to the conventional floor plans, which are spacious and comfortable and provide useful features like master suites and spacious great rooms. Imagine starting your day with a cup of coffee on your covered back patio while taking in the quiet neighborhood. The homes at Trailblazer Village are cozy, attractive, and meticulously constructed.
Starting At
3M+
Lot Size
6,526 - 9,906
Mainhouse
2,447 – 3,994
Stories
2
Bedrooms
3 - 5
Garage
2 Car
Features
ADU options available
Search Homes
​Project Progress

03/2025
-
Lot 2 paint completed​
-
Lot6 HVAC
-
Railing system for pump






























02/2025
-
Pump testing completed
-
​Deep clean rechecked
-
​Flat paved driveway completed​
-
Lot 5 hidden door and accent wall installed as rendered
-
​Lot 4 paving completed
-
Pump Testing
-
​107/109 ADU all passed inspection
-
Lot 3 and Lot 5 paint completed












01/2025
-
Pulled cable and replaced one power pole
-
​Electrical work was done
-
​PGE installed the meter
-
Passed meter release inspection
-
HVAC/ELE testing completed
-
​Pedestal electrical meter was installed
-
Electrical, HVAC, and fire sprinkler testing
-
​Lot 4/5 ADU power hookup
-
Planning inspection completed
-
​Lots 1-5 passed fire inspection
-
​Backyard stormwater treatment completed
-
​Lot 4 solar panel inspection completed
























12/2024
-
Mold inspection at lot 4
-
Shower Pan Inspection at Lot 6
-
Passed all PG&E inspection
-
Carpet installed
-
​Under Island Plumbing had been cut off
-
​Added Lot 1 handrails​​



























11/2024
-
Lot1-5 finishes installation.
-
Lot 4/5 exterior paint.
-
Driveway curb pour concrete.
-
Trailblazer first base.
-
Parking base rock.
-
Bio retention trench and rough grading.
-
Plants at public area,and site clean.
-
Lot 1 water meter install
-
Valley gutter and grading, and asphalt
-
​Sidewalk pour concrete
-
Passed Sidewalk Inspection
-
Passed PG&E final inspection































10/2024
-
Passed street light base inspection
-
​Passed water line inspection
-
Backfill
-
Water pipe installation
-
Roof installation
-
Street curb form
-
Bioretention pipe trench
-
Lot1-5 Exterior Condensers done
-
Right Side Curb form installation
-
Lot 1 Exterior Paint
-
Electrical Finish Fixures
-
Lot4/5 ADU and HVAC, Solar Panel Rack
-
Lot 1-5 Kitchen Appliance
-
Paver
-
Lot 1-2 Exterior Paint; Driveway Base; Solar Panel Rack; Biorention Trench; Interior Finishes Stuff













09/2024
-
Waterline installation
-
​Lot 1-5 casing and baseboard
-
Lot 4/5 ADU window and insulation
-
Lot 4/5 casing and baseboard
-
Lot 4/5 insulation
-
Lot 1/2 shower valve
-
Lot 6 sheetrock tape and sand
-
Lot 4 cabinet install
-
Lot 1 countertop









08/2024
-
Grading​
-
​Lot 6 Drywall
-
Cabinet Installation Lot 1 & 2
-
Hauling Dirts
-
​Lot 6 Flooring
-
​Sidewalk and compaction inspection
-
Electric Underground Installation
-
Transformer Installation
-
Lot 6 Stone Veneer Installation









07/2024
-
Lot 4/5 ADU framing
-
Lot 5 interior door
-
Onsite storm pump station installation
-
Lot1 subfloor repair
-
Lot4/5 interior door
-
Lot 6 water pipe relocated
-
​Storm pump station
-
Lot 4 bathroom tiles
-
Storm water pump station​












06/2024
-
Lot 2/3/4 bathroom tile
-
Lot 6 stucco
-
Lot1 stucco finish coat
-
Lot4/5 Adu rebar
-
Offsite joint trench
-
Offsite Pothole
-
Lot 4 tile
-
Lot 6 stucco
-
Off site storm and sewer
-
Lot4/5 ADU framing
-
Lot5 bathroom tile
-
Lot3/5main panel









05/2024
-
Lot1 stucco
-
Lot 2sheetrock
-
Lot 4/5 ADU underground plumbing
-
West valley pre construction meeting
-
Site clean
-
Lot 4/5 stucco lath
-
Lot 4/5/6 siding
-
Lot 2/3 stucco site clean
-
Lot 2/3 Sheetrock taping
-
Site clean
-
Lot2/3/4/5 fire sprinkler pipe relocate
-
Lot2/3 bathroom wall tile
-
Lot 4 bathroom tile
-
Lot 5 stucco finish coat
-
Lot 6 stucco lath
-
Lot 4/5 ADU foundation
-
Off site joint trench
-
Lot2/3 bathroom wall tile
-
Lot 4 bathroom tile
-
Lot 5 stucco finish coat
-
Lot 4/5 ADU foundation
-
Off site joint trench







04/2024
-
lot 2/3 sheetrock
-
lot4 inside clean
-
lot5 sheetrock
-
Joint trench
-
lot 3 stucco
-
lot1-3 shower water proof
-
lot1/2 sheetrock tape
-
lot2/3 bathroom water proof
-
joint trench backfill
-
lot 6 mep framing inspection
-
foundation overpour demolition
-
Lot1 stucco
-
Lot2 Sheetrock sanding
-
Lot 3 foundation
-
Lot5 tub change to shower
-
Lot4/5 ADU foundation form
-
Lot6 tub
-
Joint trench









03/2024
-
sewer trench backfill
-
lot5 porch and garage floor concrete
-
lot6 scaffold
-
storm trench dewater
-
Lot 2/3/6 framing correct
-
lot1/2 insulation
-
lot4/5 framing change
-
storm trench
-
lot1-2insulation
-
lot6 stucco lath
-
storm drain install







.jpeg)
02/2024
-
lot1/2/3 ele
-
lot4/5 plumbing
-
lot 4/5 siding
-
lot 4 framing correcting

01/2024
-
Fire sprinkler inspection
-
Lot1 Rough MEP
-
Lot4 Rough MEP
-
Lot5 Rough MEP
-
Lot6 Rough MEP


12/2023
-
Lot2/3 fire sprinkler inspection
-
Lot 1 HVAC
-
Lot4 MEP
-
Lot5 MEP
-
Lot6 MEP




11/2023
-
Lot1 Second-floor Nailing Inspection/Joint trench
-
Lot 2 Window Install/Roof Paper
-
Lot 3 Passed the Shear Wall and Truss
-
Lot 4 Truss and Sheathing
-
Lot 5 Truss Installation
-
Lot 6 Second-floor Framing






10/2023
-
Lot 1,Lot 2, Lot 3 & Lot 6 Start Framing







09/2023
-
Lot 1 underfloor framing
-
Lot 2/3/4/5 second-floor framing
-
Lot4/5 passed subfloor inspection
-
Pass 4/5 second subfloor nailing city inspection








08/2023
-
Lot 1-6 Commencement of implementation of foundation construction


06/2023
-
Pre-sale
-
Obtaining on-site land leveling permits
-
Commencement of construction
-
Obtain off-site construction encroachment permit
02/2023
Application Submission by the Department of
Real Estate (DRE)
01/2023
Submission of planning amendments
12/2022
-
Mechanical, Electrical and Plumbing
-
(MEP) Design Approved
-
Building Permit Approval
11/2022
-
Approved by City Council Consent
-
New street name approved - Trailblazer
-
Demolition permit approved
10/2022
-
Recording of vacancies and status of deeds of dedication
09/2022
-
Off-site construction plans resubmitted
-
On-site construction plan resubmission
-
Passed Planning Commission review
08/2022
-
Receive application form from the Department of Real Estate (DRE)
-
SARC passed
03/2022
-
Demolition commenced
-
Site construction plan resubmitted
-
PW issues site construction plans
-
Project website goes live
01/2022
Excavation and occupation permit
11/2021
-
Submission of topographic maps
-
Submission of on-site land leveling permit
-
Submission of off-site construction plan
08/2021
-
Acquisition date
-
​Tree report completed
-
Soil report complete
-
California Environmental Quality Act (CEQA) passed

Lot 1 Sold
Lot 5 Sold
Lot 6 Sold
Why Choose Us
We Provide Full Service at Every Step

Trusted By Clients
You are treated professionally from the minute you have your first interaction with one of our representatives. We are here to provide an experience that is unmatched and to always surpass your expectations.

Wide Range Of Properties
Looking for more properties? We have a broad selection to choose from that will suit your style, preference and budget range. Connect with our representatives to guide you on your choices!

Financing Made Easy
Owning a property made easy! RateDNA is one of the fastest-growing mortgage brokers in California and provides all various programs to all home buyers and investors.